Parks Wharf Berth 1 Remediation Works

Indianic were contracted to inspect and plan a remediation program for a land backed berth Parks 1 after an incident with a non-navy commercial vessel. The works included pile removal, fabrication of new piles and the driving on the new piles. We then removed and replaced all the timber that formed the fender backing system and walkways. We completed the work in 5 days, 16 days ahead of schedule with an allocated time of 21 days. This was due to the close relationship with our sub-contractors and the multi skilled workforce.

 